(a) Definitions. In this section:
(1) Commission. The term Commission means the Federal Energy Regulatory Commission.
(2) Environmental review. The term environmental review means the process of preparing, for a proposed agency action in accordance with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.)—
(A) an environmental impact statement;
(B) an environmental assessment;
(C) a categorical exclusion; and
(D) a finding of no significant impact.
(3) Federal authorization. The term Federal authorization has the meaning given that term in section 15(a) of the Natural Gas Act (15 U.S.C. 717n(a)).
(4) Project-related environmental review. The term project-related environmental review means any environmental review required to be conducted with respect to the issuance of an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f).
(b) Commission responsibilities. In acting as the lead agency under section 15(b)(1) of the Natural Gas Act (15 U.S.C. 717n(b)(1)) for the purposes of complying with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) with respect to an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f), the Commission shall, in accordance with this section and other applicable Federal law—
(1) be the only lead agency;
(2) coordinate as early as practicable with each agency designated as a participating agency under subsection (d)(3) to ensure that the Commission develops information in conducting its project-related environmental review that is usable by the participating agency in considering an aspect of an application for a Federal authorization for which the agency is responsible; and
(3) take such actions as are necessary and proper to facilitate the expeditious resolution of its project-related environmental review.
(c) Deference to Commission. In making a decision with respect to a Federal authorization required with respect to an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f), each agency shall give deference, to the maximum extent authorized by law, to the scope of the project-related environmental review that the Commission determines to be appropriate.
(d) Participating agencies
(1) Identification. The Commission shall identify, not later than 30 days after the Commission receives an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f), any Federal or State agency, local government, or Indian Tribe that may issue a Federal authorization or is required by Federal law to consult with the Commission in conjunction with the issuance of a Federal authorization required for such authorization or certificate.
(2) Invitation
(A) In general. Not later than 45 days after the Commission receives an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f), the Commission shall invite any agency identified under paragraph (1) to participate in the review process for the applicable Federal authorization.
(B) Deadline. An agency invited under subparagraph (A) shall submit a response to the Commission by not later than 30 days after the date the invitation is received, which may be extended by the Commission for good cause for a period of not more than 15 days.
(C) Failure to meet deadline. If an agency invited under subparagraph (A) fails to meet the deadline described in subparagraph (B), the agency shall not be considered a participating or cooperating agency.
(3) Designation as participating agencies. Not later than 60 days after the Commission receives an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f), the Commission shall designate an agency identified under paragraph (1) as a participating agency with respect to that application unless the agency informs the Commission, in writing, by the deadline established pursuant to paragraph (2)(B), that the agency—
(A) has no jurisdiction or authority with respect to the applicable Federal authorization;
(B) has no special expertise or information relevant to any project-related environmental review; or
(C) does not intend to submit comments for the record for the project-related environmental review conducted by the Commission.
(e) Comment deadline. The Commission is not required to respond to comments regarding a Federal authorization submitted after the applicable comment period is over.
(f) Water quality impacts
(1) In general. Notwithstanding section 401 of the Federal Water Pollution Control Act (33 U.S.C. 1341), a certification under such section shall not be required with respect to a Federal authorization.
(2) Coordination. With respect to any environmental review for a Federal authorization to conduct an activity that will directly result in a discharge into the navigable waters (within the meaning of the Federal Water Pollution Control Act (33 U.S.C. 1251 et seq.)), the Commission shall identify as an agency under subsection (d)(1) the State in which the discharge originates or will originate, or, if appropriate, the interstate water pollution control agency having jurisdiction over the navigable waters at the point where the discharge originates or will originate.
(3) Proposed conditions. A State or interstate agency designated as a participating agency pursuant to paragraph (2) may propose to the Commission terms or conditions for inclusion in an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f) that the State or interstate agency determines are necessary to ensure that any discharge described in paragraph (2) conducted pursuant to such authorization or certification will comply with the applicable provisions of sections 301, 302, 303, 306, and 307 of the Federal Water Pollution Control Act (33 U.S.C. 1311, 1312, 1313, 1316, 1317).
(4) Commission consideration of conditions. The Commission may include a term or condition in an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f) proposed by a State or interstate agency under paragraph (3) only if the Commission finds with clear and convincing evidence that the term or condition is necessary to ensure that any discharge described in paragraph (2) conducted pursuant to such authorization or certification will comply with the applicable provisions of sections 301, 302, 303, 306, and 307 of the Federal Water Pollution Control Act (33 U.S.C. 1311, 1312, 1313, 1316, 1317).
(5) Commission denial of certificate. The Commission may deny an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f) based on water quality concerns only if the Commission finds with clear and convincing evidence that the proposed project cannot comply with the applicable provisions of sections 301, 302, 303, 306, and 307 of the Federal Water Pollution Control Act (33 U.S.C. 1311, 1312, 1313, 1316, 1317).
(g) Schedule
(1) Deadline for Federal authorizations. A deadline for a Federal authorization required with respect to an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f) set by the Commission under section 15(c)(1) of that Act (15 U.S.C. 717n(c)(1)) shall be not later than 90 days after the Commission completes its project-related environmental review, unless an applicable schedule is otherwise established by Federal law.
(2) Concurrent reviews. Each Federal and State agency that may consider an aspect of an application for a Federal authorization required with respect to an application for authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f) shall—
(A) carry out the obligations of that agency under applicable law; and
(B) in considering an aspect of an application for a Federal authorization required with respect to an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f), shall—
(i) carry out the obligations of that agency under applicable law concurrently, and in conjunction with, the project-related environmental review conducted by the Commission, pursuant to a schedule established by the Commission not to exceed 270 days, but subject to the condition that the Commission may, at the request of the agency and for good cause, grant a single 60-day extension; and
(ii) not less often than once every 90 days, transmit to the Commission a report describing the progress made in considering such application for a Federal authorization.
(3) Failure to meet deadline. If a Federal or State agency, including the Commission, fails to meet a deadline for a Federal authorization set forth in the schedule established by the Commission under section 15(c)(1) of the Natural Gas Act (15 U.S.C. 717n(c)(1)), not later than 5 days after such deadline, the head of the relevant Federal agency (including, in the case of a failure by a State agency, the Federal agency overseeing the delegated authority) shall notify Congress and the Commission of such failure and set forth a recommended implementation plan to ensure completion of the action to which such deadline applied.
(h) Consideration of applications for Federal authorization
(1) Issue identification and resolution
(A) Identification. Federal and State agencies that may consider an aspect of an application for a Federal authorization shall identify, as early as possible and not later than 90 days after receipt of a request for the Federal authorization, any issues of concern that may delay or prevent an agency from working with the Commission to resolve such issues and granting the Federal authorization.
(B) Issue resolution. The Commission may forward any issue of concern identified under subparagraph (A) to the heads of the relevant agencies (including, in the case of an issue of concern that is a failure by a State agency, the Federal agency overseeing the delegated authority, if applicable) for resolution.
(2) Remote surveys
(A) In general. If a Federal or State agency considering an aspect of an application for a Federal authorization requires the person applying for the Federal authorization to submit data, the agency shall—
(i) consider any such data gathered by aerial or other remote means that the person submits; and
(ii) accept aerial surveys in absence of clear and convincing evidence.
(B) Conditional approval. The agency may grant a conditional approval for a Federal authorization based on data gathered by aerial or remote means, conditioned on the verification of such data by subsequent onsite inspection if the Commission determines that an onsite inspection is likely to materially alter the final determination of the Commission or the grant of the certificate.
(3) Application processing. The Commission, and Federal and State agencies, may allow a person applying for a Federal authorization to fund a third-party contractor to assist in reviewing the application for the Federal authorization.
(i) Accountability, transparency, efficiency
(1) In general. For an application for an authorization under section 3 of the Natural Gas Act (15 U.S.C. 717b) or a certificate of public convenience and necessity under section 7 of that Act (15 U.S.C. 717f) that requires multiple Federal authorizations, the Commission, with input from any Federal or State agency considering an aspect of the application, shall track and make available to the public on the website of the Commission information related to the actions required to complete the Federal authorizations.
(2) Inclusions. The information described in paragraph (1) shall include the following:
(A) The schedule established by the Commission under section 15(c)(1) of the Natural Gas Act (15 U.S.C. 717n(c)(1)).
(B) A list of all the actions required by each applicable agency to complete permitting, reviews, and other actions necessary to obtain a final decision on the application.
(C) The expected completion date for each action described in subparagraph (B).
(D) A point of contact at the agency responsible for each such action.
(E) In the event that an action is still pending as of the expected date of completion, a brief explanation of the reasons for the delay.
(j) Strengthening judicial review of Natural Gas Act projects. Section 19 of the Natural Gas Act (15 U.S.C. 717r) is amended—
(1) in subsection (b), in the eighth sentence, by striking certification and all that follows through the period at the end and inserting certification as provided in section 1254 of title 28, United States Code.; and
(2) in subsection (d)—
(A) in paragraph (3), in the first sentence, by striking If the Court finds and inserting the following: Except as provided in paragraph (6), if the Court finds; and
(B) by adding at the end the following:
(6) Exception for certain orders or actions
(A) In general. Notwithstanding any other provision of this section, for petitions challenging an order or action taken by the Commission under section 3 or section 7, the court may not set aside, vacate, or otherwise void that order or action.
(B) Court action. Notwithstanding chapter 7 of title 5, United States Code, the Court shall remand the proceeding, without vacatur or injunction, to the applicable Federal or State agency to take appropriate action if the Court finds that an order or action described in paragraph (1)—
(i) would prevent the construction, expansion, or operation of the facility subject to section 3 or 7; and
(ii)
(I) is inconsistent with applicable Federal law; or
(II) is not supported by clear and convincing evidence.